Main Menu
Search
promise zone facebook
Capital Project Update - June 2018
 
UPK Addition
The UPK addition nears completion with the steel erected, exterior sheathing and air barriers in place and the new brick veneer installed.  The new windows and EPDM roof are also installed.  In the coming weeks, the exterior mosaic tile and architectural panels will be in place to trim out the addition.  Inside, all ductwork and heating is complete, with plumbing following close behind.  Lights are installed and operational, and other electrical fixtures will be complete soon.  Walls are installed and taped, with painting complete in the two classrooms.  The vinyl flooring work is complete and terrazzo flooring work will start by the end of the month.  Final trims and fixtures are expected to be in place by mid to late June, with only minor items left to complete the addition.
  
  
 High School 90's Wing
Renovations in the High School 90's wing have been moving forward on second shift and the work is more than 50% complete.  Each completed room is receiving new celings, flooring, paint and LED lighting.  The new fire-rated door frames are complete and await new doors to be hung with upgraded hardware that includes a visible locked/unlocked indicator function.  This new function will improve security within the classrooms.  Rooms in the 90's wing will also be receiving a new whiteboard material atop the old chalkboards, giving the rooms a much more updated look.
 
Exterior Security Cameras
New security cameras have been installed on the CEA building and the High School, as well as on the poles in the parking lots.  This will provide increased security on the campus. 
 
Exterior Canopy
Sidewalk canopy work had begun, with all structural work complete, CEA framing complete and the HS framing started.  Soon, the finished panels will be installed at the canopy and the new lights will be functional.
 
Landscaping and Sitework
Landscaping, new underground utilities, and other sitework is nearly complete. Sitework for the new UPK addition, along with restoration of the staging area where construction trailers were set up will be complete this summer.
 
Roofing
The High School roofing and edge metal trim has been completed, and miscellaneous structural roof reinforcing will be completed this summer.
 
Miscellaneous
The new, upgraded electrical service at the High School is complete. New scoreboards were installed in the TRA gymnasium, and scoreboards were moved from TRA to the CEA gymnasium.
 
Summer Work  
The following items will be completed over the summer of 2018:

    - New HVAC in auditorium
    - Art Room renovations
    - UPK tricycle track
    - Remaining 90's wing work
    - Remaining landscaping

10 Keibel Rd. Whitney Point, NY 13862  |  P 607.692.8202  |  F 607.692.4434
STUDENTS         STAFF         PARENTS         COMMUNITY
View text-based website